Priority list has already been prepared and beneficiaries will be selected from there.
After proper enquiry, beneficiaries will be registered in the AWASSOFT.
GEO tagging will be done against all eligible registered beneficiary through AWAS App.
Sanction will be done from District end. Total amount-120000/- +90days unskilled labour cost from MGNREGA.
After getting sanction from district end, order sheet and Fund Transfer Order(FTO) of 1st instalment , amounting to Rs. 40000.00, will be generated from Panchayat Samity end.
After signing and submitting FTOs, facilitators will be sent to the beneficiary to know whether fund has been credited to the beneficiary’s account or not.
If fund is credited, facilitator will insist the beneficiary to start the work and he will monitor the work so that fund is utilised in a shortest time.
From 1st instalment fund upto plinth level construction must be done.
Then inspection will be made. Both inspection report and photograph of the construction will be uploaded in the AWASSOFT. Photograph will be taken only through smart phone using AWASApp.
Again order sheet and FTO for 2nd. Instalment, amounting to Rs. 30000.00, will be prepared and signed.
facilitators will be sent to the beneficiary to know whether fund has been credited to the beneficiaries account or not.
If fund is credited, facilitator will insist the beneficiary to complete the work upto lintel level with this fund. He will help the beneficiary to do the work.
After completion upto lintel level, an inspection will be made. Both inspection report and photograph of the construction will be uploaded in the AWASSOFT.
Then again order sheet and FTO for 3rd instalment, amounting to Rs. 40000.00, will be prepared and signed.
facilitators will again be sent to the beneficiary to know whether fund has been credited to the beneficiary’s account or not.
If fund is credited, facilitator will insist the beneficiary to complete the house with this fund. He will help the beneficiary to do the work.
After completing the house, again an inspection will be made. Both inspection report and photograph of the complete house will be uploaded in the AWASSOFT.
Then again order sheet and FTO for 4th. instalment, amounting to Rs. 10000.00, will be prepared and signed.
Facilitator will monitor whether 4th instalment has been credited to beneficiary’s account. He will also monitor whether the beneficiary is getting convergence facilities from MGNREGA, SBM, PMUY(Pradhan Mantri Ujjwala Yojana) etc.